
Building Update 9/25/24
The finishing touches and landscaping are moving quickly! The painters are here this week to finish up in the new building and to paint the wall in the Terrace Room...

Building Update 9/11/24
The kitchen installation is getting finished today. The fence along the west property line is going up. And grading is continuing. Contact Shari Loe or Franklin...

Building Update 9/4/24
In the past week, all of the kitchen equipment is continuing to be hooked up, the flooring through out the building will be fully installed by the end of the week,...

Building Update 8/28/24
In the past week, all of the kitchen equipment was installed (not necessarily hooked up); the flooring in the Welcome Gallery is almost fully installed; additional...

Building Update 7/17/24
The building site has been very busy! The concrete for the ramp from the Meeting Room vestibule has been poured. The front sidewalks are framed and being poured....